New Subdivision Map Act Extension Bill Signed

New Subdivision Map Act Extension Bill Signed

On Friday (July 15), Governor Brown signed into law AB 208 (Fuentes), which extends
for two years the life of those tentative and vesting tentative maps that were still alive on July 15,
2011 (the date the new law took effect) and that would have otherwise expired before January 1,
2014.

AB 208 builds upon two earlier legislative extensions given during this prolonged
economic downturn: (1) the 24-month extension granted by AB 333 (Fuentes) in 2009; and
(ii) the 12-month extension granted by SB 1185 (Lowenthal) in 2008. With nearly 2,500
approved tentative maps representing nearly 330,000 housing units in California, this measure is
significant.

AB 208 creates new Government Code section 66452.23, which recognizes that this
extension is available in addition to all of the other extensions (or “stays”) already recognized
by the Subdivision Map Act (i.e., Sections 66452.6, 66452.11, 66452.13, 66452.21, 66452.22,
and 66463.5). So, for example, even if a tentative map qualifies for the new 24-month extension
granted by AB 208, this would not preclude the subdivider from employing the phased final map
extensions provided under Government Code section 66452.6(a)(1) and any applicable litigation
stays pursuant to Government Code section 66452.6(c).

When calculating whether a tentative map would otherwise expire before January 1, 2014
and thereby be eligible for AB 208’s two-year extension, one must include any discretionary
extension granted by a city or county pursuant to Government Code sections 66452.6(e) or
66463.5(c) on or before July 15, 2011, and any extensions effectuated through the filing of one
or more multiple final maps pursuant to Government Code section 66452.6(a) on or before July
15, 2011. One is not required to count any time that the map’s life is stayed by litigation or a
development moratorium pursuant to Government Code sections 66452.6 or 66463.5.

Like AB 333, AB 208 includes provisions that change the “one bite of the apple” rules
set forth in Government Code section 65961 in two ways. First, it shortens from five to three
years the period of time after the recordation of the final map during which new conditions
cannot be imposed on a project. Second, AB 208 provides that for any tentative or parcel map
subject to AB 208’s two-year extension, Section 65961 does not prohibit a local agency “from
levying a fee or imposing a condition that requires the payment of a fee … upon the issuance of
a building permit, including, but not limited to, a fee defined in Section 66000″ [the Mitigation
Fee Act]. (Gov. Code § 65961(f).) Thus, a local agency may attempt to impose fees or fee-based
conditions during building permit issuance. The “legality” of such local agency efforts would
depend on the facts of each case.

If you own property with a current tentative or vesting tentative map or other
entitlements, please contact us to discuss whether your maps are subject to AB 208 and how this
important new legislation affects the expiration dates of your entitlements. We are also available
to discuss any related issues, such as AB 208’s impact on vested rights and how to document the application of AB 208 to your existing maps.

Leave a Reply

Your email address will not be published. Required fields are marked *